DR.3.1.1 Each team is responsible for confirming that their documents have been properly uploaded or submitted and that the deadlines have been met.
DR.3.1.2 Prior to the Submission Deadline:
a. Documents may be uploaded at any time
b. Uploads may be replaced with new uploads without penalty
DR.3.1.3 If a Submitted Document revision is requested by the Reviewer, a new Submission Deadline for the revised document may apply
DR.3.1.4 Teams will not be notified if a document is submitted incorrectly.